FY12 MILCON Wing Headquarters Design Surveys, 92nd ARW & ANG 141st ARW, Fairchild AFB, WA;


White Shield provided design mapping services for this project that involves demolition of a 3,546 sm existing building area and 7,437 sm of existing pavements, and construction of a new 2,491 sm Wing Headquarters Facility. The primary facilities included the new headquarters building, parking lots, landscaping, site improvements, and anti-terrorism/force protection measures. White Shield surveyors established project control derived from primary horizontal and vertical control acquired from the USACE, acquired Utility Atlas and recorded the data from the USACE, and utilized a private utility locating company to locate services. Topographic mapping of the primary project area was provided at 2-foot contour intervals, 1”=40’ scale. Utilities to be capped surrounding and serving Building 2185 were also located and mapped. Deliverables included Digital Terrain Models (DTM) and AutoCAD drawing files of the surveyed areas.